Public accountability dashboard

What LAMP Texas is doing for Liberty County, in numbers.

Jobs, local contracts, construction, environment and community commitments. Every figure shows where it came from, how sure we are, and every change made to it. Ask a question and we answer in public.

Last updated 1 Nov 2026

Construction

Construction milestones

Planned and actual dates. When a target moves, the original target stays on this page.

  1. DoneReported by LAMP

    Site acquired

    Actual
    Q3 2024

    701 acres in unincorporated Liberty County, inside the Houston metro.

  2. DoneReported by LAMP

    Groundbreaking and site preparation

    Actual
    January 2025

    Earthwork, grading, utilities, roads, drainage, and detention ponds began.

  3. DoneVerified

    Preliminary plat approved by Liberty County

    Actual
    July 2026

    A county approval that lets the campus be divided into parcels. Public record at Liberty County.

  4. DoneReported by LAMP

    Vertical construction of the main building began

    Actual
    July 1, 2026

    Steel erection started the same week. This is when the campus became visible from Highway 90.

  5. ProjectedPlanned

    Power phase 1: initial deployment

    Capacity
    60 MW
    Target
    October 2026
    • October 2026: Phase 1 power, 60 MW: target online (Target)

    From LAMP Infrastructure, approved records only. Not yet verified.

  6. PlannedPlanned target

    First parcels ready for tenants

    Target
    Q4 2026

    When the first manufacturers can move in.

  7. PlannedPlanned target

    Phase 1 site, building, and utility work complete

    Target
    December 2026

    The target for finishing all Phase 1 construction.

  8. ProjectedPlanned

    Power phase 2: expansion

    Capacity
    240 MW
    Target
    2027
    • 2027: Planned capacity of 240 MW, campus total (Target)

    From LAMP Infrastructure, approved records only. Not yet verified.

  9. ProjectedPlanned

    Power phase 3: scale-up

    Capacity
    600 to 1,000 MW or more
    Target
    2028 to 2030

    From LAMP Infrastructure, approved records only. Not yet verified.

  10. ProjectedPlanned

    Power phase 4: long-term planned capacity

    Capacity
    Up to 3 GW
    Target
    2030 and beyond

    From LAMP Infrastructure, approved records only. Not yet verified.

Infrastructure figures

Construction photos

Approved photos and updates from the site.

No approved photo updates yet.

Permits and documents

Permits, reports and plans that LAMP staff added to the public library.

No permits or documents have been added yet.