Public accountability dashboard

What LAMP Texas is doing for Liberty County, in numbers.

Jobs, local contracts, construction, environment and community commitments. Every figure shows where it came from, how sure we are, and every change made to it. Ask a question and we answer in public.

Last updated 1 Nov 2026

Overview

Overview

How to read this page

  • VerifiedConfirmed by a document, a public record or a third party.
  • Reported by LAMPPublished by LAMP. The source is linked when available.
  • Planned targetA goal or a target date. Not done yet.
  • PendingNot published yet. The reason is shown.

Corrections are permanent. They cannot be edited or deleted. Correction history

Latest changes

Every published change, newest first.

  1. 1 Nov 2026Imported from the earlier dashboardWater quality monitoring LAMP-MON-0003
  2. 1 Nov 2026Imported from the earlier dashboardNoise monitoring LAMP-MON-0002
  3. 1 Nov 2026Imported from the earlier dashboardAir quality monitoring LAMP-MON-0001
  4. 1 Nov 2026Imported from the earlier dashboardAir, noise, and water quality monitoring LAMP-M-0026
  5. 1 Nov 2026Imported from the earlier dashboardConstruction trucks routed away from residential streets LAMP-M-0025
  6. 1 Nov 2026Imported from the earlier dashboardEnvironmental studies completed before construction LAMP-M-0024

Jobs & Contracts

Jobs & Contracts

Local jobs and local suppliers

What "local" means here

Local workers
LAMP has not published its definition yet. Until it does, each figure says which area it counts.
Local suppliers
LAMP has not published its definition yet. Until it does, each figure says which area it counts.

Local jobs

Contracts and vendors

Construction

Construction

Construction milestones

Planned and actual dates. When a target moves, the original target stays on this page.

  1. DoneReported by LAMP

    Site acquired

    Actual
    Q3 2024

    701 acres in unincorporated Liberty County, inside the Houston metro.

  2. DoneReported by LAMP

    Groundbreaking and site preparation

    Actual
    January 2025

    Earthwork, grading, utilities, roads, drainage, and detention ponds began.

  3. DoneVerified

    Preliminary plat approved by Liberty County

    Actual
    July 2026

    A county approval that lets the campus be divided into parcels. Public record at Liberty County.

  4. DoneReported by LAMP

    Vertical construction of the main building began

    Actual
    July 1, 2026

    Steel erection started the same week. This is when the campus became visible from Highway 90.

  5. ProjectedPlanned

    Power phase 1: initial deployment

    Capacity
    60 MW
    Target
    October 2026
    • October 2026: Phase 1 power, 60 MW: target online (Target)

    From LAMP Infrastructure, approved records only. Not yet verified.

  6. PlannedPlanned target

    First parcels ready for tenants

    Target
    Q4 2026

    When the first manufacturers can move in.

  7. PlannedPlanned target

    Phase 1 site, building, and utility work complete

    Target
    December 2026

    The target for finishing all Phase 1 construction.

  8. ProjectedPlanned

    Power phase 2: expansion

    Capacity
    240 MW
    Target
    2027
    • 2027: Planned capacity of 240 MW, campus total (Target)

    From LAMP Infrastructure, approved records only. Not yet verified.

  9. ProjectedPlanned

    Power phase 3: scale-up

    Capacity
    600 to 1,000 MW or more
    Target
    2028 to 2030

    From LAMP Infrastructure, approved records only. Not yet verified.

  10. ProjectedPlanned

    Power phase 4: long-term planned capacity

    Capacity
    Up to 3 GW
    Target
    2030 and beyond

    From LAMP Infrastructure, approved records only. Not yet verified.

Infrastructure figures

Construction photos

Approved photos and updates from the site.

No approved photo updates yet.

Permits and documents

Permits, reports and plans that LAMP staff added to the public library.

No permits or documents have been added yet.

Community Impact Map

Environment

Environment

Environmental measurements

Charts appear only for real readings that staff publish.

No measurements published yet

Monitoring

Planned monitoring is not the same as a working instrument. Each point says which it is.

  • PlannedLAMP-MON-0001

    Air quality monitoring

    LAMP plans to publish monitoring results once operations begin, with the method used for each reading.

  • PlannedLAMP-MON-0002

    Noise monitoring

    LAMP plans to publish monitoring results once operations begin, with the method used for each reading.

  • PlannedLAMP-MON-0003

    Water quality monitoring

    LAMP plans to publish monitoring results once operations begin, with the method used for each reading.

Figures and milestones

  1. DoneReported by LAMP

    Environmental studies completed before construction

    Actual
    Q1 2025

    Studies done during master planning. Documents will be linked here as LAMP releases them.

  2. In progressReported by LAMP

    Construction trucks routed away from residential streets

    Target
    Ongoing

    Reduces noise, dust, and road wear in neighborhoods. Quieter hydraulic pile drivers were used for foundations.

Community

Community

Public Commitment Ledger

Each promise has a permanent number. The original words always stay visible, and every change has an explanation.

No commitments published yet. Commitments are added after staff approval.

Community figures and milestones

  1. In progressReported by LAMP

    Committee of the Community

    Target
    2026

    A standing group of Liberty County residents who meet with LAMP leadership. Meeting notes will be posted here.

  2. In progressReported by LAMP

    STEM program for local schools

    Target
    2026

    Connects Liberty County students with industry careers. Participation numbers will be added when available.

  3. In progressReported by LAMP

    Local hiring is the first priority

    Target
    Ongoing

    LAMP's public commitment. The "Local hires" number above is how the community can check it.

Community Impact Map

Construction areas, truck routes, monitoring and planned infrastructure that LAMP staff marked as public. Reported concerns are shown only after approval and without personal details.

Community Impact Map
Illustration of the published site plan. Not to scale. Positions are approximate.
  • Campus parcels (published plan)
  • Rail line
  • Construction area (0)
  • Truck route (0)
  • Planned infrastructure (0)
  • Monitoring point (0)
  • Community concern (0)

Map items

No map items published yet.

Reported concerns

No concerns published yet.

Public Questions

Public Questions

Answered questions

Response time (Our target): We aim to answer within 10 business days.

No questions answered yet.