A long-term industrial platform

LAMP is not a collection of separate projects. It is a long-term industrial platform designed to grow with the companies that choose to build here and with the broader needs of American industry.

The steel frame of a campus building under construction, with a crane, containers and a pond beside it

The case in brief

Rare earth magnets in many shapes laid out on a dark surface

A strategic need

The United States has spent the last several decades watching critical manufacturing capacity move offshore. Rare earth magnets. Precision components. Defense-adjacent supply chains. The strategic vulnerability this created is well documented.

The LAMP site in Liberty County seen from the air, with earthworks, foundations and rows of containers

Scale that is hard to find

701 contiguous acres near a major American metro is uncommon. Most large industrial sites within the Houston area are either already developed, fragmented across multiple owners, or located in areas with significant infrastructure constraints.

Solar panels beside a concrete pad on the LAMP site, seen from above

Power on site

LAMP is planned behind the meter: on-site generation serves its main operations, which limits additional demand on the regional grid. Liberty County is in the MISO South power market.

Two white water storage tanks on the LAMP site, with a steel building frame behind them

Shared infrastructure

Tenants at LAMP share infrastructure, reduce capital expenditure, and operate within an ecosystem where progress in one industry strengthens the next.

A large steel-framed building with a finished white roof and a crane beside it, seen from above

Already under construction

Construction on the campus is active. The infrastructure being installed today, including utilities, access, and core manufacturing facilities, is designed to support not just Phase 1 but the decades of expansion that follow. All Phase 1 site, building and utility works are targeted for completion in December 2026.

The dome of the Texas State Capitol with the Texas flag

The Texas advantage

Texas offers a favorable environment for advanced manufacturing, with no personal or corporate income tax (businesses pay the Texas franchise tax), a pro-business regulatory environment, a long history of energy production and industrial development, and a state government that actively supports domestic manufacturing investment.

Who we talk with

LAMP Texas welcomes conversations with long-term capital: sovereign wealth funds, institutional investors, real estate investors and EB-5 regional centers. Every conversation starts with the form at the end of this page.

Sovereign wealth funds

A 701-acre campus near Houston, planned around on-site power and shared infrastructure for American manufacturing. We welcome introductions from sovereign funds that invest in industrial infrastructure in the United States.

Pension funds, insurers and endowments

For institutions with long horizons: an industrial platform built infrastructure first, with construction under way today and room to grow phase by phase.

Real estate investors and developers

Of the campus's 701 acres, JLL has exclusive rights to 550 acres and 4 million square feet of space. Real estate investors and developers can start with the JLL page, or write to us below.

EB-5 regional centers and investors

LAMP has no EB-5 offering today and makes no claim that an investment in the project would qualify under the EB-5 program. Regional centers and their investors who want to learn about the project are welcome to write.

The campus in numbers

701acres
Master-planned campus
60MW Projected
From October 2026
240MW Projected
In 2027
Up to 3GW
Long-term planned capacity

From vision to reality

LAMP Texas has progressed through a series of planned development phases, transforming from a long-term vision into an active industrial campus.

  1. The land of the future campus before construction, seen from the air
    Q3 2024

    Site acquisition

    LAMP Texas secured the project site and completed the initial land acquisition, establishing the foundation for long-term campus planning and future industrial development.

  2. A site plan on an easel inside a building under construction
    Q4 2024 – Q1 2025

    Planning & engineering

    Master planning, engineering design, environmental studies, infrastructure planning, and utility coordination were completed to prepare the campus for construction.

  3. Safety and construction signs laid out on a concrete floor
    January 2025

    Groundbreaking and site preparation

    LAMP broke ground in January 2025. Site work followed: earthwork, grading, utilities, roads, drainage, detention ponds and preparation for vertical construction.

  4. Bulldozers and excavators lined up on the site at dusk
    2025 – 2026

    County and state approvals

    LAMP is working through county and state approvals. Liberty County approved the preliminary plat in July 2026, and each permit is listed with its date as it is granted.

  5. Two white water storage tanks on the LAMP site, with a steel building frame behind them
    July 2026 – present

    Vertical construction

    Vertical construction of the main building began on 1 July 2026; steel erection followed that week. Buildings, utilities and supporting infrastructure continue to take shape.

  6. Rendering of the completed campus from the air, with solar panels on the roofs and in the fieldsRendering
    Future development

    Multi-phase campus expansion

    As future phases are completed, LAMP Texas will continue expanding its infrastructure, manufacturing capabilities, and industrial ecosystem while creating new opportunities for businesses, partners, and the Liberty County community.

LAMP TexasLiberty Advanced Manufacturing and Power

The site at a glance

LAMP (Liberty Advanced Manufacturing & Power) is a master-planned, infrastructure-first innovation campus developed by BaRupOn LLC in Liberty County, Texas.

Satellite map of the Houston region with LAMP Texas marked on Highway 90, between Houston and BeaumontEnlarge
Land
701 acres in Liberty County, inside the Houston metropolitan area.
Leasing
Of the campus's 701 acres, JLL has exclusive rights to 550 acres and 4 million square feet of space. Sites are offered on 19 parcels.
Location
Unincorporated Liberty County. Industrial development is subject to applicable regulatory approvals.
Power
Planned behind the meter. Power is delivered in phases: 60 MW from October 2026, 240 MW in 2027 and 600 to 1,000 MW or more from 2028 to 2030. Long-term planned capacity is up to 3 GW.
Transmission
Existing 138 kV transmission 1.15 miles from the site. 345 kV interconnection capability planned.
Natural gas
Adjacent 30-inch natural gas pipeline. 30,000 MMBtu a day initial delivery capacity.
Fiber
Multiple tier-1 providers, entrances from three sides at full buildout, carrier-neutral fiber facility on site.
Water
More than 50 million gallons of planned water storage, with detention ponds and rainwater capture.
Access
Highway 90 adjacent. Rail available on site. About 40 minutes from downtown Houston; George Bush Intercontinental Airport within reach.
Delivery
Target fast-track delivery in 10 to 14 months.
Developer
BaRupOn LLC

LAMP TexasFM 2830, Liberty, TX 77575+1 (855) 227-8766info@lamptx.comlamptx.com

Power, phase by phase

LAMP is planned behind the meter: on-site generation serves its main operations, which limits additional demand on the regional grid. Liberty County is in the MISO South power market.

240 MW Projectedin 2027

  1. Phase 1

    60MW Projected

    Initial deployment

    Target online October 2026

    Natural gas generation in a combined-cycle configuration.

    Planned

  2. Phase 2

    240MW Projected

    Expansion

    Target online 2027

    Additional natural gas generation plus infrastructure.

    Planned

  3. Phase 3

    600–1,000MW+ Projected

    Scale-up

    Target online 2028 to 2030

    Further expansion and additional capacity.

    Long-term capacity

  4. Phase 4

    Up to 3GW

    Campus buildout

    Target online 2030 and beyond

    Long-term planned capacity is up to 3 GW.

    Long-term capacity

Each figure is the total planned capacity of the campus in that period, not an addition to the phase before. Targets are not firm commitments.

Planned capacity and status

The power plan phase by phase, with its status as LAMP publishes it. Planned capacity is a projection; firm capacity is what a signed agreement commits.

PhasePlanned capacity, campus totalTargetStatusFirm capacity
Phase 160 MW ProjectedOctober 2026PlannedSet in a signed agreement
Phase 2240 MW Projected2027PlannedSet in a signed agreement
Phase 3600 to 1,000 MW or more Projected2028 to 2030Long-term capacitySet in a signed agreement
Phase 4Up to 3 GW Projected2030 and beyondLong-term capacitySet in a signed agreement

Each figure is the total planned capacity of the campus in that period, not an addition to the phase before. Targets are not firm commitments. Every figure here is planned capacity, a projection from current plans. Firm capacity, allocation and dates are set only in a signed agreement, after a technical review.

Two Phase 1 dates, two milestones

  1. October 2026

    First power

    The first 60 MW of power is targeted from October 2026.

  2. December 2026

    All Phase 1 works

    All Phase 1 site, building and utility works are targeted for completion in December 2026.

The two dates are different milestones. Both are targets.

LAMP Texas

Phase 1 power status report

60 MW, planned behind the meter

Report date
No stage date published yet
Basis
Information published by LAMP and JLL
Status
Planned

Current energization target

October 2026 (target). The first 60 MW of power is targeted from October 2026.

Completed

  • Load flow and short circuit analysis completed

Stage dates not yet published

  • Equipment procured
  • Delivered
  • Installed
  • Commissioning
  • Tested
  • Operational

Design basis, verified at commissioning

  • N+1 redundancy
  • Island-mode capable
  • Black-start capable
  • 99.999% reliability target

Grid and fuel

  • Existing 138 kV transmission, about 1.15 miles from the campus
  • 345 kV interconnection capability planned
  • 30-inch natural gas pipeline adjacent to the campus
  • 30,000 MMBtu a day of initial delivery capacity

Each stage shows its date once it is verified.

Stage by stage

The date each phase reached each stage, as LAMP publishes it once the stage is verified.

Last update No stage date published yet

  1. Phase 160 MW Projected

    1. Equipment procuredNot yet published
    2. DeliveredNot yet published
    3. InstalledNot yet published
    4. CommissioningNot yet published
    5. TestedNot yet published
    6. OperationalNot yet published
  2. Phase 2240 MW Projected

    1. Equipment procuredNot yet published
    2. DeliveredNot yet published
    3. InstalledNot yet published
    4. CommissioningNot yet published
    5. TestedNot yet published
    6. OperationalNot yet published
  3. Phase 3600 to 1,000 MW or more Projected

    1. Equipment procuredNot yet published
    2. DeliveredNot yet published
    3. InstalledNot yet published
    4. CommissioningNot yet published
    5. TestedNot yet published
    6. OperationalNot yet published
  4. Phase 4Up to 3 GW Projected

    1. Equipment procuredNot yet published
    2. DeliveredNot yet published
    3. InstalledNot yet published
    4. CommissioningNot yet published
    5. TestedNot yet published
    6. OperationalNot yet published

Fuel supply, phase by phase

Natural gas is the fuel of the first phases. The supply in place today, and the plan for each later phase as it is approved.

30-inchnatural gas pipeline adjacent to the campus

30,000MMBtu a day of initial delivery capacity

  1. Pipeline
  2. Delivery point
  3. On-site generation
  4. Campus distribution
  5. Tenant facilities
  • Delivery point adjacent to the campus
  • Redundant supply options available
  • Dual gas supply paths, with on-site storage options
PhasePlanned capacity, campus totalFuel supply planContracted delivery
Phase 160 MWPublished once approvedPublished once approved
Phase 2240 MWPublished once approvedPublished once approved
Phase 3600 to 1,000 MW or morePublished once approvedPublished once approved
Phase 4Up to 3 GWPublished once approvedPublished once approved

The fuel supply of each later phase is published once its plan is approved. Contracted volumes, redundancy and added pipeline capacity are confirmed in the technical review of each phase.

Companies and partners at LAMP

  1. Neodyte

    Neodyte is BaRupOn's rare earth permanent magnet manufacturing venture, based at the LAMP campus.

  2. QYK

    QYK is developing a proposed 7,000 metric tons per year Methacrylic Acid (MAA) manufacturing facility at LAMP, with future expansion planned to 30,000 metric tons.

  3. Solideon

    Solideon, an aerospace and advanced manufacturing company founded by former SpaceX, Virgin Orbit, and Rocket Lab engineers, is bringing its 3D printing technology to LAMP.

  4. CK Power

    Spin Energy Storage is part of LAMP's energy infrastructure, working alongside partners like CK Power to strengthen the campus's power reliability.

Partnerships

Fiber on site
Banking partner
Gas supply partnership
 

Designed for long-term growth

LAMP is being developed through a phased strategy that prioritizes operational readiness at every stage. Each phase is planned to support the next, ensuring the campus can expand in scale and capability without compromising the infrastructure commitments made to future tenants.

Rendering for reference only. Final design, features, and specifications subject to change.

Construction progress

Follow the latest construction milestones, infrastructure improvements, and development activity across the campus.

Photos as of October 2, 2026

Documents

  • LAMP Texas brochure
    PDF, September 2026
    Download
  • Fact sheet
    Two pages: the site, its power, the parcels and the leasing contacts.
    Download
  • Investor presentation
    The campus, the case for it, and its infrastructure, slide by slide.
    Download

Institutional access

Data room for qualified investors and lenders

Investors and lenders in serious discussions can ask for controlled access to substantiated technical, permitting, land, power, commercial and financial information. Access is given after review and a confidentiality agreement.

Request data room access
  1. 01

    Request access

    Use the form below and choose "someone requesting data room access". Say who you represent and what you are assessing.

  2. 02

    Review

    LAMP reviews each request before any material is shared.

  3. Confidentiality agreement

    A confidentiality agreement is signed before access is given.

  4. 04

    Access

    Material is shared under the agreement, as each item is approved for release.

What the data room holds

Corporate

The developer, ownership and the structure of the project.

Land and title

Surveys, title, the plat and the acreage schedule.

Engineering

Design basis, site studies and the engineering of each phase.

Power and fuel

The power plan by phase, its status, and the fuel supply plan.

Permits and approvals

Applications and approvals, each with its date and status.

Construction and schedule

Monthly engineering reports and the construction schedule.

Leasing

The parcel schedule and the leasing structure through JLL.

Financial

Financial information, shared only under a confidentiality agreement.

Investor material is not an offer of securities.

Request investor information

We read every message and respond to every serious inquiry.

LAMP will not make commitments it cannot keep.

Fields marked * are needed to send the form.

This page gives general information about LAMP Texas. It is not an offer to sell, or a solicitation of an offer to buy, any security, and it is not investment advice. Statements about plans, timing and capacity describe current intentions and may change. Investor material is not an offer of securities.