LAMP Texas
Phase 1 power status report
60 MW, planned behind the meter
Current energization target
October 2026 (target). The first 60 MW of power is targeted from October 2026.
Completed
- Load flow and short circuit analysis completed
Stage dates not yet published
- Equipment procured
- Delivered
- Installed
- Commissioning
- Tested
- Operational
Design basis, verified at commissioning
- N+1 redundancy
- Island-mode capable
- Black-start capable
- 99.999% reliability target
Grid and fuel
- Existing 138 kV transmission, about 1.15 miles from the campus
- 345 kV interconnection capability planned
- 30-inch natural gas pipeline adjacent to the campus
- 30,000 MMBtu a day of initial delivery capacity
Each stage shows its date once it is verified.