Explore the LAMP campus

The 701-acre LAMP campus in Liberty County, Texas, in one place: the site plan with its 19 parcels, power and water, the targeted delivery of each parcel, and how construction is going.

The building from high above, with a pond and rows of containersThe LAMP site, October 2026

701acres in Liberty County, Texas

550acres marketed by JLL, on 19 parcels

60 MW Projectedof power from October 2026

Dec 2026Phase 1 target

The site plan

Choose a zone, a delivery date or a parcel. Switch the planned infrastructure lines on and off, and put parcels on a shortlist to ask about them together.

Earliest delivery
Show
SSSTEC-1TEC-2TEC-3TEC-4MFG-2MFG-1MFG-3MFG-4MFG-5IND-1IND-2IND-3IND-4IND-5IND-6IND-7IND-8IND-9IND-10Solar fieldSolar fieldFuture expansionFuture expansionWater capture and treatmentRail lineU.S. Highway 90Generation plantFuture generationUtility interconnection345 kV, plannedFiber hubIn servicePlannedPlannedNatural gas pipeline
Four advanced technology parcels on the west side, five advanced manufacturing parcels in the middle, ten industrial and support parcels below them, two solar fields to the north, water capture and treatment in the south-east corner, and the rail line and Highway 90 along the southern edge.

19 parcels shown

ShortlistIntended useBuilding, share of siteMaximum coverageConstruction-readyUtilities-readyLease status
Advanced technology±32 acres235,000 SFabout 17%40%Q4 2026To be confirmedTo be confirmedAvailable for lease
Advanced technology±32 acres235,000 SFabout 17%40%Q4 2026To be confirmedTo be confirmedAvailable for lease
Advanced technology±77 acres560,000 SFabout 17%40%Q1 2027To be confirmedTo be confirmedAvailable for lease
Advanced technology±76 acres555,000 SFabout 17%40%Q1 2027To be confirmedTo be confirmedAvailable for lease
Advanced manufacturing±45 acres325,000 SFabout 17%35%Q4 2026To be confirmedTo be confirmedAvailable for lease
Advanced manufacturing±29 acres210,000 SFabout 17%35%Q4 2026To be confirmedTo be confirmedAvailable for lease
Advanced manufacturing±29 acres200,000 SFabout 16%35%Q1 2027To be confirmedTo be confirmedAvailable for lease
Advanced manufacturing±45 acres330,000 SFabout 17%35%Q1 2027To be confirmedTo be confirmedAvailable for lease
Advanced manufacturing±45 acres325,000 SFabout 17%35%Q2 2027To be confirmedTo be confirmedAvailable for lease
Industrial and support±14 acres105,000 SFabout 17%30%Q1 2027To be confirmedTo be confirmedAvailable for lease
Industrial and support±14 acres105,000 SFabout 17%30%Q1 2027To be confirmedTo be confirmedAvailable for lease
Industrial and support±14 acres105,000 SFabout 17%30%Q1 2027To be confirmedTo be confirmedAvailable for lease
Industrial and support±14 acres105,000 SFabout 17%30%Q1 2027To be confirmedTo be confirmedAvailable for lease
Industrial and support±14 acres105,000 SFabout 17%30%Q1 2027To be confirmedTo be confirmedAvailable for lease
Industrial and support±14 acres100,000 SFabout 16%30%Q2 2027To be confirmedTo be confirmedAvailable for lease
Industrial and support±14 acres100,000 SFabout 16%30%Q2 2027To be confirmedTo be confirmedAvailable for lease
Industrial and support±14 acres100,000 SFabout 16%30%Q2 2027To be confirmedTo be confirmedAvailable for lease
Industrial and support±14 acres100,000 SFabout 16%30%Q2 2027To be confirmedTo be confirmedAvailable for lease
Industrial and support±14 acres100,000 SFabout 16%30%Q2 2027To be confirmedTo be confirmedAvailable for lease

Ground lease or build-to-suit on all parcels. All parcels are owned by BaRupOn. Maximum coverage is the largest share of a parcel that buildings may cover. The largest building shown covers a smaller share: its floor area divided by the land of the parcel, rounded. The plan is an illustration redrawn from the site plan of the JLL marketing document. It is not to scale, and areas are approximate. "Available for lease" means the parcel can be leased now. It does not mean the parcel is ready to build: construction-ready and utilities-ready dates show in their own columns once published, and the earliest delivery dates are targets.

Targeted delivery by quarter

Each bar is one quarter, made of the parcels whose earliest delivery is targeted by then. Dates are targets and can change.

  • Advanced technology zone
  • Advanced manufacturing zone
  • Industrial and support
  1. TEC-1, ±32 acres, 235,000 SF.TEC-2, ±32 acres, 235,000 SF.MFG-1, ±45 acres, 325,000 SF.MFG-2, ±29 acres, 210,000 SF.

    138 acres4 parcels, 1,005,000 SF

    138 of 550 acres by then

  2. TEC-3, ±77 acres, 560,000 SF.TEC-4, ±76 acres, 555,000 SF.MFG-3, ±29 acres, 200,000 SF.MFG-4, ±45 acres, 330,000 SF.IND-1, ±14 acres, 105,000 SF.IND-2, ±14 acres, 105,000 SF.IND-3, ±14 acres, 105,000 SF.IND-4, ±14 acres, 105,000 SF.IND-5, ±14 acres, 105,000 SF.

    297 acres9 parcels, 2,170,000 SF

    435 of 550 acres by then

  3. MFG-5, ±45 acres, 325,000 SF.IND-6, ±14 acres, 100,000 SF.IND-7, ±14 acres, 100,000 SF.IND-8, ±14 acres, 100,000 SF.IND-9, ±14 acres, 100,000 SF.IND-10, ±14 acres, 100,000 SF.

    115 acres6 parcels, 825,000 SF

    550 of 550 acres by then

Power, phase by phase

Power is delivered in phases: 60 MW from October 2026, 240 MW in 2027 and 600 to 1,000 MW or more from 2028 to 2030.

  1. Phase 1

    60MW Projected

    Initial deployment

    Target online October 2026

    Natural gas generation in a combined-cycle configuration.

    Planned

  2. Phase 2

    240MW Projected

    Expansion

    Target online 2027

    Additional natural gas generation plus infrastructure.

    Planned

  3. Phase 3

    600–1,000MW+ Projected

    Scale-up

    Target online 2028 to 2030

    Further expansion and additional capacity.

    Long-term capacity

  4. Phase 4

    Up to 3GW

    Campus buildout

    Target online 2030 and beyond

    Long-term planned capacity is up to 3 GW.

    Long-term capacity

Each figure is the total planned capacity of the campus in that period, not an addition to the phase before. Targets are not firm commitments.

Planned capacity and status

The power plan phase by phase, with its status as LAMP publishes it. Planned capacity is a projection; firm capacity is what a signed agreement commits.

PhasePlanned capacity, campus totalTargetStatusFirm capacity
Phase 160 MW ProjectedOctober 2026PlannedSet in a signed agreement
Phase 2240 MW Projected2027PlannedSet in a signed agreement
Phase 3600 to 1,000 MW or more Projected2028 to 2030Long-term capacitySet in a signed agreement
Phase 4Up to 3 GW Projected2030 and beyondLong-term capacitySet in a signed agreement

Each figure is the total planned capacity of the campus in that period, not an addition to the phase before. Targets are not firm commitments. Every figure here is planned capacity, a projection from current plans. Firm capacity, allocation and dates are set only in a signed agreement, after a technical review.

Two Phase 1 dates, two milestones

  1. October 2026

    First power

    The first 60 MW of power is targeted from October 2026.

  2. December 2026

    All Phase 1 works

    All Phase 1 site, building and utility works are targeted for completion in December 2026.

The two dates are different milestones. Both are targets.

LAMP Texas

Phase 1 power status report

60 MW, planned behind the meter

Report date
No stage date published yet
Basis
Information published by LAMP and JLL
Status
Planned

Current energization target

October 2026 (target). The first 60 MW of power is targeted from October 2026.

Completed

  • Load flow and short circuit analysis completed

Stage dates not yet published

  • Equipment procured
  • Delivered
  • Installed
  • Commissioning
  • Tested
  • Operational

Design basis, verified at commissioning

  • N+1 redundancy
  • Island-mode capable
  • Black-start capable
  • 99.999% reliability target

Grid and fuel

  • Existing 138 kV transmission, about 1.15 miles from the campus
  • 345 kV interconnection capability planned
  • 30-inch natural gas pipeline adjacent to the campus
  • 30,000 MMBtu a day of initial delivery capacity

Each stage shows its date once it is verified.

Stage by stage

The date each phase reached each stage, as LAMP publishes it once the stage is verified.

Last update No stage date published yet

  1. Phase 160 MW Projected

    1. Equipment procuredNot yet published
    2. DeliveredNot yet published
    3. InstalledNot yet published
    4. CommissioningNot yet published
    5. TestedNot yet published
    6. OperationalNot yet published
  2. Phase 2240 MW Projected

    1. Equipment procuredNot yet published
    2. DeliveredNot yet published
    3. InstalledNot yet published
    4. CommissioningNot yet published
    5. TestedNot yet published
    6. OperationalNot yet published
  3. Phase 3600 to 1,000 MW or more Projected

    1. Equipment procuredNot yet published
    2. DeliveredNot yet published
    3. InstalledNot yet published
    4. CommissioningNot yet published
    5. TestedNot yet published
    6. OperationalNot yet published
  4. Phase 4Up to 3 GW Projected

    1. Equipment procuredNot yet published
    2. DeliveredNot yet published
    3. InstalledNot yet published
    4. CommissioningNot yet published
    5. TestedNot yet published
    6. OperationalNot yet published

What the dates mean

A date in the parcel schedule is a target for one stage of a parcel. Five stages lead from land to an occupied building.

  1. 1

    Land available

    The parcel can be leased or bought, as it is.

  2. 2

    Construction-ready

    The pad is graded and accessible, ready for a building to start.

  3. 3

    Utilities at the parcel

    Power, water and fiber are brought to the edge of the parcel.

  4. 4

    Building complete

    A building on the parcel is finished and inspected.

  5. 5

    Occupancy

    The tenant moves in and starts operations.

Building figures are building potential: the largest building a parcel could hold under its maximum coverage. They are not completed or occupiable space.

Acreage schedule

How the land of the campus is counted. Lines without a figure are published once they are confirmed.

LandAcresNotes
Campus, gross land controlled701The whole LAMP campus.
Marketed by JLL, gross, 19 parcels550Of the campus's 701 acres, JLL has exclusive rights to 550 acres and 4 million square feet of space.
Other campus land151The rest of the campus.
Net usable land by parcel
ParcelGross acresNet usable acres
TEC-1±32To be confirmed by survey
TEC-2±32To be confirmed by survey
TEC-3±77To be confirmed by survey
TEC-4±76To be confirmed by survey
MFG-1±45To be confirmed by survey
MFG-2±29To be confirmed by survey
MFG-3±29To be confirmed by survey
MFG-4±45To be confirmed by survey
MFG-5±45To be confirmed by survey
IND-1±14To be confirmed by survey
IND-2±14To be confirmed by survey
IND-3±14To be confirmed by survey
IND-4±14To be confirmed by survey
IND-5±14To be confirmed by survey
IND-6±14To be confirmed by survey
IND-7±14To be confirmed by survey
IND-8±14To be confirmed by survey
IND-9±14To be confirmed by survey
IND-10±14To be confirmed by survey

How net usable acreage is counted

Net usable land is the gross parcel area less every part that cannot carry a building. Each line is confirmed by survey before it is published.

  1. Gross parcel area, 19 parcels

    550 acres

  2. Floodplain

    Published site conditions: Flood Zone X, minimal risk. Any floodplain inside a parcel is mapped by survey.

    To be confirmed by survey

  3. Drainage and detention

    Ponds and channels that hold and carry storm water.

    To be confirmed by survey

  4. Utility and access easements

    Strips reserved for pipelines, power lines and access.

    To be confirmed by survey

  5. Infrastructure corridors

    Roads, utility corridors and generation sites of the campus.

    To be confirmed by survey

  6. Other development constraints

    Setbacks, wetlands or other limits found by survey.

    To be confirmed by survey

  7. Net usable land

    To be confirmed by survey

Gross acres are the parcel areas of the JLL schedule. Net figures leave out land that cannot be built on. All areas are approximate.

The infrastructure

What is planned, and what is built so far.

Solar panels beside a concrete pad on the LAMP site, seen from above

Power

Power is delivered in phases: 60 MW from October 2026, 240 MW in 2027 and 600 to 1,000 MW or more from 2028 to 2030. Long-term planned capacity is up to 3 GW.

Rendering of the completed campus from the air, with solar panels on the roofs and in the fieldsRendering

Behind the meter

LAMP is planned behind the meter: on-site generation serves its main operations, which limits additional demand on the regional grid. Liberty County is in the MISO South power market.

Two white water storage tanks on the LAMP site, with a steel building frame behind them

Water

More than 50 million gallons of planned water storage, with detention ponds and rainwater capture. The main bodies of two steel water tanks were completed in July 2026 and work began on a third.

Rows of green and red containers on the site

Rail and roads

A rail spur connects to the nearby Union Pacific line. Trucks reach the campus by FM 2830 and State Highway 770, routed away from residential streets.

The land of the future campus before construction, seen from the air

Land

JLL markets 550 of the 701 acres, in 19 parcels. The acreage schedule on the Leasing page shows how the land is counted.

Construction so far

  1. Bulldozers and excavators lined up on the site at dusk

    January 2025

    LAMP broke ground in January 2025.

  2. Two white water storage tanks on the LAMP site, with a steel building frame behind them

    July 2026

    Vertical construction of the main building began on 1 July 2026; steel erection followed that week.

  3. Earthworks and equipment beside the building, seen from the airOctober 2026

    December 2026

    All Phase 1 site, building and utility works are targeted for completion in December 2026.

Construction progress

Follow the latest construction milestones, infrastructure improvements, and development activity across the campus.

Photos as of October 2, 2026

Location and access

Liberty County sits within the Houston metropolitan area, putting LAMP Texas within reach of one of the largest industrial and manufacturing ecosystems in the United States.

Approximate drive times

  • 45minGeorge Bush Intercontinental Airport (IAH)
  • 40minDowntown Houston
  • 50minPort Houston, Bayport Container Terminal
  • 30–45minRegional workforce centers
  • Highway 90 adjacent
  • Rail available on site
  • Unincorporated Liberty County

Located in unincorporated Liberty County, with industrial development subject to applicable regulatory approvals.

Why Liberty

Ask about a site

Tell us what you are planning. We read every message and bring in the JLL team.

Fields marked * are needed to send the form.

Global Innovation Lab

Apply to the Innovation Lab

Have a technology to pilot at LAMP? Send an application. Every application is subject to review and availability.

Start an application

Figures describe plans and targets and can change. Parcel names on this website can differ from the names in other documents.